BEACHFILL PROJECT UPDATE - REVISED PROJECT SCHEDULE!
The dredge Illinois is in place in Corson's Inlet adjacent to Strathmere. Beachfill operations have progressed quicker than anticipated, and the beach work in Strathmere is expected to be complete by the weekend of August 8-9.
Based on this, the beachfill operation is now scheduled to commence in Sea Isle around August 9, at the north end of the island (1st Street). The beachfill will proceed from 1st to 15th Street; then move downtown and proceed from 40th to 52nd Street. As work proceeds and the dredge's production is evaluated, the schedule will be updated on Channel 2 and the City's website.
Questions regarding the project can be directed to Sea Isle City Business Administrator, George Savastano, at 609-263-4461, ext. 223.